METHOD STATEMENT - Offloading and installation of heat pumps - Installation of pipe work in the riser - Plant Room Installation - Flush and Commissioning

1.            INTRODUCTION

This Health & Safety Plan has been developed to cover the installation of the heatpumps into the building, the completion of the plant room and the commissioning. It is based on current knowledge and will be reviewed and amended, if necessary, as work progresses and circumstances dictate.

save 100%
Details
SKU SKU479371
Weight 0.02 Kgs
 
Market price: £15.00
Our price: FREE to download
 
Quantity 1 (this product is downloadable)
: *
: *
: *
Type the characters you see in the picture:


*
KITCHEN EQUIPMENT - REFRIGERATION - REFRIGERATOR
NKW Reversible Chiller Submittal Data Models NKW090 & NKW130 50Hz R410a English Language/SI Units
Hazardous substances
KITCHEN EQUIPMENT - REFRIGERATION - REFRIGERATOR NKW Reversible Chiller Submittal Data Models NKW090 & NKW130 50Hz R410a English Language/SI Units Hazardous substances
£6.00
 
AIR HANDLING PLANT ANCILLARIES - ACCESS DOORS
PUMPS DOMESTIC
H.V. SWITCHGEAR - 11kV VACUUM CIRCUIT BREAKER
AIR HANDLING PLANT ANCILLARIES - ACCESS DOORS PUMPS DOMESTIC H.V. SWITCHGEAR - 11kV VACUUM CIRCUIT BREAKER
£6.00
£6.00
£6.00
 
Fire Safety Risk Assesment for large places of assembly
Lifts
ELV CIRCUITS - LEAD ACID BATTERIES
Fire Safety Risk Assesment for large places of assembly Lifts ELV CIRCUITS - LEAD ACID BATTERIES
£6.00
£6.00
£6.00

Product rating

Customer Reviews